Currently Birmingham’s tallest office building at 26 storeys high. We provided various scaffolding solutions throughout every phase of the construction process including;
- Safety edge protection
- Independent access scaffolds for internal blockwork
- Cantilevered truss out scaffolds to lift shafts
- Cantilevered beamed gantries
- Cantilevered truss outs
- Cuplock staircases
Works were full of logistical challenges due to the building taking up the entire footprint of the site.
The showstopper for this project was certainly the huge heavy duty beamed protection gantry to ‘The Winter Garden’.